Major Road & Drainage Improvements

Project Name Status Contract Price Contractor Consultant Notice to Proceed Projected Completion Date Project Files
Road Projects
Airport Road Connector - Phase 1  Bidding Process  $2.2M - est  TBD  Allsouth       
Airport Rd Connector (Lowe Pond Dredge and Fill)  Under Construction  $468,000.00  Advanced Quality Construction  STP  08/03/2011  11/15/2011   
Airport Road Connector - Phase 2A Clearing and Grubbing  Bidding Process  $875.000.00  TBD  Allsouth       
Airport Road Connector - Phase 2B  Planning  TBD  TBD  Allsouth       
Bootlegger (Hwy 21 to 1077)  On Hold  $760,000.00  TBD  NY       
Covington Bypass South (Hwy 21 to Bootlegger)  Under Construction  $2,567,359.67  Amtek  Richard C. Lambert  04/26/2010  01/10/2012  Covington Bypass Project Location  
East Howze Beach Road - Raising  Design  $1M  TBD  STP       
Frances Rd @ Bootlegger  2012 Project  $1,000,000.00  TBD  NY & Associates       
Fishing Pier  Under Construction  $485,000.00  Gill's Crane  STP  08/18/2011  12/06/2011   
Holiday Square Blvd Turn Lane  Bidding Process  $500,000.00  TBD  STP       
Huntwyck Village Drainage Improvements - Phase 2  ROW Acquisition  TBD  TBD  Digital Design       
Huntwyck Village Drainage Improvements - Phase 1  Bidding Process  $3,000,000.00  TBD  Digital Design      Huntwyck Village Drainage  
Hwy 1077 Widening Part A (I-12 to 1085)  On Hold  $2M - est  TBD  Atlas       
Hwy 1077 Widening Part C (1085/1077 Intersection Improvements)  On Hold  $10M - est  TBD  PEEC       
Hwy 190 @ Bogue Falaya Bridge  On Hold  TBD  TBD  Kyle & Associates       
Hwy 59 @ LA 1088  Design / Planning  $479,000  TBD  Kelly McHugh       
Koop Drive Extension East  Under Construction  $426,615.00  Leon Lowe  RCL  06/30/2011  11/28/2011   
Krental Rd @ Hwy 434 & Fishery Hatchery  Under Construction  $338,995.20  Huey Stockstill  STP  08/10/2011  12/09/2011   
LA 1085 - Hwy 22 to 1077  On Hold  $760,000.00  TBD  NY & Associates       
US 190 (Fremeaux @ Summit Blvd)  Under Construction  $137,249.00  Stranco Inc.  JV Burkes  06/01/2011  11/28/2011   
Veterans Cemetary Road  Design / Planning  $1M  TBD  TBD       
Voters Rd @ LA 433 Improvements  Under Construction  $257,460.00  Kass Brothers  Principle  09/12/2011  01/09/2012   
Drainage Projects
Hwy 434 Retention Lake  Design  $361,538.75  Allsouth  TBD       
Fountains Drainage  Obtaining Work Quotes  $80,000.00  STP  TBD       
Lowe Pond Canal Erosion  Under Construction  $534,000.00  ERS Incorporated  STP  09/26/2011  03/26/2012   
Schneider Canal Back Flow Protection  Contract Review  TBD  McDonald Construction, Inc. of Slidell  RCLC       
Schneider Canal Pump Station Improvements  Design  TBD  TBD  GEC       
South Slidell Levee Segment 3A  Permitting  TBD  TBD  STP       
South Slidell Levee 3B  Under Construction  $595,927.00  Bertucci  STP  08/04/2011  11/11/2011   
South Slidell Levee 4  Design / Planning  TBD  TBD  STP       
Timber Branch Pond  Bidding Process  $175,000  TBD  WINK      Timber Branch Pond Project  
Ski Pond Rd (Ben Thomes Rd)  Under Construction  $20,089.00  Nick's Dozer  JV Burkes  10/03/2011     
DOTD Projects
Airport Rd - I-10 (I-12 Widening)  Under Construction  $25,664,489.16  James Construction Group  DOTD  03/01/2011  07/01/2012   
I-10 SW Frontage Road Extension  Under Construction  $2,989,156.75  Boh Bros  DOTD  02/24/2011  11/30/2011   
LA 433 @ Voters Road  Under Construction  $1,488,301.60  Barriere  Principal  08/09/2010  09/30/2011   
Robert Blvd. @ Brownswitch  Under Construction  $1,010,393.33  RCS Contractors, Inc.  Atlas  07/19/2010  09/30/2011  Robert Road @ Brownswitch  
Roundabout @ East JCT LA 434  Out to Bid  $500,000 - 1M  TBD  DOTD       
Tammany Trace / Lacombe Trailhead  Out to Bid  $100,000 - 250,000  McDonald Construction, Inc. of Slidell  DOTD       
Miscellaneous Projects
Cloverland Rd Proposed Canal  Planning  $627,332.00  TBD  TBD       
Cypress Park Drainage Improvements  Planning  $1,556,021.00  TBD  TBD       
Little Bayou Castine Headwater Improvements  Planning  $638,420.00  TBD  TBD       
Completed Projects
Arrowwood Pond Weir Replacement Project  Complete  $157,151.00  Advance Quality Construction  WINK  08/30/2010  11/28/2010  Arrow Wood Weir Project Location  
Camp Salmen  Complete  $863,651.00  Amtek  STP  07/17/2009  06/15/2010   
Abita Springs Sidewalk Program  Complete  $260,284.52  Leon Lowe & Sons  DOTD       
Cleo @ Hwy 11  Complete  $122,018.50  Stranco Inc.  STP       
STP Regional Airport Improvements  Complete  TBD  Amtek         
Haas Road Pond Fence  Complete  $200,000.00  TBD  STP       
Hwy 59 @ I-12 Improvements  Complete  $2,945,458.00  Barriere  DOTD    05/24/2010   
Brewster Rd Extension Lane Separator  Complete  $21,094.00  Richard Price  STP       
I-59 @ Military Road  Complete  1.2M estimate  Boh Brothers  Buchart Horn  09/09/2009  10/09/2009  I-59 @ Military  
Browns Village  Complete  $278,764.50  Huey Stockstill, Inc.  STP  09/15/2010  12/11/2010   
Woodridge Subdivision Drainage Ditch  Complete  $949,500.00  Coast to Coast  Pinnacle  06/23/2010  10/20/2011   
Koop Drive Extension West  Complete  $749,633.85  Larry Loyd  STP  08/03/2009  07/06/2010  Koop West Project Location  
Parc du Lac Weir  Complete  $127,423.50  Stranco Inc.  STP  03/14/2011  06/13/2011  Parc du Lac Weir Project  
District 62 Emergency Repair Project  Complete  $4,165,464.95  Huey Stockstill, Inc.  DOTD  07/13/2010  05/01/2011   
Robert Rd. Area Drainage  Complete  $58,512.00  Advanced Quality Construction  KLL / STP  03/28/2011  05/27/2011  Robert Road Drainage Study  
South Slidell Levee  Complete  $596,000  Leon Lowe  STP  09/20/2010  02/28/2011   
Event Center Blvd (Lakeshore Blvd North)  Complete  $145,175.00  Creek Constrcution  STP  01/03/2011  02/17/2011   
I-12 Noise Barrier Replacement (US 11 - LA 1091)  Complete  $1 - 2.5M  RMD Holdings  DOTD  11/08/2010  08/11/2011   
Haas Rd. Widening  Complete  $1,222,723  Leon Lowe  JV Burkes  09/15/2010  04/08/2011  Haas Road Widening  
LA 21 @ Brewster Road  Complete  $1,483,955.55  Barriere  Duplantis Group  07/26/2010  03/11/2011   
LA 21 @ I-12  Complete  $4,995,995.97  Barriere  Richard Lambert  07/26/2010  03/11/2011   
LA 1088 Interchange / Route I-12  Complete  $12,303,475.00  Barriere  DOTD  10/25/2009  05/01/2011   
Lake Road @ Powell Canal  Complete  $1,085,765.95  Key Constructors  DOTD  05/12/2010     
Military @ Brownswitch  Complete  $650,933.42  Three C's  Atlas  08/02/2010  07/31/2011   
Industrial Drive  Complete  $194,541.00  Barriere  STP  10/01/2010  12/31/2010   
I-12 @ US 11  Complete  $107,000  Barriere  BKI  10/05/2010  01/01/2011   
West JCT LA 21 - South JCT US 190  Complete  $842,513.02  Barriere  DOTD  05/14/2010  08/01/2010   
Koop Drive Right Turn  Complete  $22,440.00  Boh Bros  STP  05/22/2011  06/08/2011   
US 11 @ I-12 Interchange  Complete  $5,099,519.00  Barriere  DOTD  09/25/2009  03/11/2011   
Lakeshore/Oak Harbor Intersection aka E. Howze Beach Rd  Complete  $434,572.04  Byron Talbot  KLL  08/09/2010  11/09/2010  E. Howze Beach Project Map  
US 190 @ Northpark  Complete  $356,954.54  Richard Price  URS  08/09/2010  03/11/2011   
Lindberg Drive Extension  Complete  $149,696.00  McDonald Construction, Inc. of Slidell  JV Burkes  01/17/2011  04/29/2011   
Mire Road Turn Lane  Complete  $68,770  Geopave  STP  03/30/2011  06/28/2011   
Million Dollar Rd  Complete  $749,236.00  Barriere  STP       
Polders Lane  Complete  $406,000.00  Stranco Inc.  Ponchartrain  05/23/2011  08/22/2011   
North Lane Paving  Complete  TBD  McDonald Construction  STP  10/11/2010  12/01/2010   
Pearl Acres Widening  Complete  $1,275,000  Leon Lowe  Aims  07/15/2010  03/15/2011  Pearl Acres Project Location  
Tantela Ranch Rd. East Extension  Complete  $195, 941.10  RJ Booty  STP  03/01/2011  06/10/2011   

Project maps will be added as they become available.

Key Description
Design Project is in the planning/design stage and may include determining project needs, logistical determinations, cost estimates etc.
Design/Row Project is in the design phase and the design is being determined by the Right of way needs.
Out to bid/ Bid under review Project is in the bid process whereby the Parish is awaiting/or evaluating bid proposals from prospective vendors on the subject project. 
ROW Determining and/or acquiring Right of way for project area.
Under Construction Project is in the construction process.