St. Tammany Parish Government - Building Excellence
Home Leadership Online Services Departments and Agencies About St. Tammany Community Resources Contact
Major Road & Drainage Improvements

Project Name Status Contract Price Contractor Consultant Notice to Proceed Projected Completion Date Project Files
Road Projects
Airport Road to Hwy 11  ROW  $13.6M - est  TBD  Allsouth       
Bootlegger (Hwy 21 to 1077)  On Hold  $760,000.00  TBD  NY       
Browns Village  Contract Review  $278,765  Huey Stockstill, Inc.  STP       
Covington Bypass South (Hwy 21 to Bootlegger)  Under Construction  $2,567,359.67  Amtek  Richard C. Lambert  04/26/2010  04/25/2011  Covington Bypass Project Location  
E. Howze Beach @ LA 433 Improvements  Design / Planning  $400,000.00  TBD  Principle       
Emerald Forest Extension  On Hold  $7.3M  RCL  TBD      Emerlad Forest  
Event Center Blvd (Lakeshore Blvd North)  Out to Bid  $50,000.00  TBD  STP       
Haas Rd. Widening  Contractor Contract Review  $1,222,723  Leon Lowe  JV Burkes      Haas Road Widening  
Harrison Avenue Extension (Phase 1)  Design (2011 Project)  $250,000.00  TBD  Kyle & Associates       
Huntwyck Village Drainage  ROW (2011 Project)  $5,000,000.00  Digital Engineering  TBD      Huntwyck Village Drainage  
Hwy 1077 Widening Part A (I-12 to 1085)  On Hold  $2M - est  TBD  Atlas       
Hwy 1077 Widening Part C (1085/1077 Intersection Improvements)  On Hold  $10M - est  TBD  PEEC       
Hwy 190 @ Bogue Falaya Bridge  On Hold  TBD  TBD  Kyle & Associates       
Industrial Drive  Out to Bid  TBD  TBD  STP       
Koop Drive Extension East  Design / Permitting (2011 Project)  $710,000.00  TBD  RCL       
Lakeshore/Oak Harbor Intersection aka E. Howze Beach Rd  Under Construction  $419,000.00  Byron Talbot  KLL      E. Howze Beach Project Map  
Learning Center  Design / Planning (2011 Project)  TBD  TBD  TBD       
Mire Road  Design  $250,000.00  TBD  STP       
North Lane Paving  Planning  TBD  McDonald Construction  STP       
Pearl Acres Widening  Under Construction  $1,275,000  Leon Lowe  Aims  07/15/2010  01/11/2011  Pearl Acres Project Location  
Tantela Ranch Rd. East Extension  Design (2011 Project)  TBD  TBD  TBD       
Drainage Projects
Arrowwood Pond Weir Replacement Project  Contractor Contract Review  $157,000  Advance Quality Construction  WINK      Arrow Wood Weir Project Location  
Cours Carson Drainage Improvements  Design / Planning  TBD  TBD  STP       
Haas Road Pond Fence  Design  $200,000.00  TBD  STP       
Lowe Pond Canal Erosion  Design  $500,000.00  TBD  STP       
Parc du Lac Weir  Design / ROW Acquisition  $300,000  TBD  STP      Parc du Lac Weir Project  
Robert Rd. Area Drainage Study  Design  $150,000  TBD  KLL / STP      Robert Road Drainage Study  
Slidell Levee  Out to Bid  $910,000  TBD  STP       
Timber Branch Pond  Design  $175,000  TBD  WINK      Timber Branch Pond Project  
DOTD Projects
Abita Springs Sidewalk Program  Contract Review  $260,284.52  Leon Lowe & Sons  DOTD       
Brownswitch @ Military  Contract Review  $650,933.42  Three C's  Atlas       
District 62 Emergency Repair Project  Contract Review  $4,165,464.95  Huey Stockstill, Inc.  DOTD  05/15/2010  11/15/2010   
Hwy 59 @ I-12 Improvements  Under Construction  $2,945,458.00  Barriere  DOTD    05/24/2010   
I-10 SW Service Road Extension  Out to Bid  $2.5 - 5M  TBD  DOTD       
I-12 Noise Barrier Replacement (US 11 - LA 1091)  Out to Bid  $1 - 2.5M  TBD  DOTD       
LA 21 @ Brewster Road  Under Contract Review  $1,483,955.55  Barriere  Duplantis Group       
LA 433 @ Voters Road  Contract Review  $1,488,301.60  Barriere  Principal       
LA 21 @ I-12  Contract Review  $4,995,995.97  Barriere  Duplantis Group       
LA 1088 Interchange / Route I-12  Under Construction  $12,303,475.00  Barriere  DOTD    02/11/2011   
Lake Road @ Powell Canal  Under Construction  $1,085,765.95  Key Constructors  DOTD  06/15/2010  12/15/2010   
Robert Blvd. @ Brownswitch  Contract Review  $1,010,393.33  RCS Contractors, Inc.  Atlas      Robert Road @ Brownswitch  
Roundabout @ East JCT LA 434  Out to Bid  $500,000 - 1M  TBD  DOTD       
Tammany Trace / Lacombe Trailhead  Out to Bid  $100,000 - 250,000  TBD  DOTD       
West JCT LA 21 - South JCT US 190  Contract Review  $842,513.02  Barriere  DOTD       
US 11 @ I-12 Interchange  Under Construction  $5,265,577.00  Barriere  DOTD  10/26/2009  06/25/2010   
US 190 @ Northpark  Contract Review  $356,954.54  Richard Price  URS       
Miscellaneous Projects
STP Regional Airport Improvements  Bids Under Review  TBD  Amtek         
Woodridge Subdivision Drainage Ditch  Under Contract Review  $949,500.00  Coast to Coast  Pinnacle       
Completed Projects
Camp Salmen  Complete  $863,651.00  Amtek  STP  07/17/2009  06/15/2010   
I-59 @ Military Road  Complete  1.2M estimate  Boh Brothers  Buchart Horn  09/09/2009  10/09/2009  I-59 @ Military  
Koop Drive Extension West  Complete  $749,633.85  Larry Loyd  STP  08/03/2009  07/06/2010  Koop West Project Location  

Project maps will be added as they become available.

Key Description
Design Project is in the planning/design stage and may include determining project needs, logistical determinations, cost estimates etc.
Design/Row Project is in the design phase and the design is being determined by the Right of way needs.
Out to bid/ Bid under review Project is in the bid process whereby the Parish is awaiting/or evaluating bid proposals from prospective vendors on the subject project. 
ROW Determining and/or acquiring Right of way for project area.
Under Construction Project is in the construction process.